Mott MacDonald Ltd
The
head office of Mott MacDonald Ltd, one of the largest firms of consulting
engineers in the UK, required the replacement of the existing R22 water
chillers, with a requested increase in output, the replacement of the main
chilled water circulating pumps, and the replacement of the existing fresh
air supply system, along with associated control valves and the installation
of a new runaround heat recovery system between the building extract systems
and the new fresh air unit.
Two new Aermec twin screw water chillers, having a total cooling output of 1000 kilowatts, were installed, using a 500 tonne telescopic crane.
In addition, we manufactured and installed new maintenance platforms and walkways to suit the layout of the new equipment, for safe maintenance.
The entire project was carried out during the latter part of the winter, and was completed in four weeks. The chillers, of course, were back in operation within five days of the contract start date.
Please contact us and we can advise you on your best options.